WATER POLICY IMPLEMENTATION PROCESS

PROTECTION AND ASSESSMENT POLICY IMPLEMENTATION TASK TEAM (PAPITT)

 

RESOURCE DIRECTED MEASURES PHASE 2 & 3

PROGRESS REPORT FOR THE PERIOD APRIL 1999 TO JUNE 1999

Contents

1. Introduction *

2. PROJECT MANAGEMENT *

2.1 Financial status *

2.2 Steering Committee *

2.3 Project office

2.4 Departmental implementation workshop *

3. progress on individual sub-projects AND ACTIVITIES *

3.1 PIENAAR RIVER PILOT STUDY *

3.2 IMPLEMENTATION STRATEGY

3.3 CLASSIFICATION

3.4 RIVERS

3.5 Groundwater *

3.6 Estuaries

3.7 Wetlands *

3.8 Capacity building *

3.9 Communication *

 

Prepared by D Grobler, IWQS

1. INTRODUCTION

This report covers the work done during the period 1 April 1999 to 30 June 1999, within Phase 2 and 3 of the project to develop Resource Directed Measures (RDM) for water resource protection.

An overview of the work to be carried out in Phases 2 and 3 of the RDM project (August 1998 to March 2000) can be found in the project terms of reference, which was included as an appendix to the progress report for August/September 1998. The terms of reference can also be found on the web page at address http://www.dwaf.gov.za/iwqs/wg/waterlaw/index.html

For more information on any of the issues in this report, contact Dr H MacKay or Mr D F Grobler, IWQS.

2. PROJECT MANAGEMENT

2.1 Financial status

The financial status of the project as at 30 June 1999 is shown in Table 1. The total amount of funding allocated to Phases 1 and 2 in the 1998/99 financial year was R960 000, allocated amongst eight specialist sub-project teams. The total amount spent on the RDM project in the 1998/99 financial year was R 954 164. The amount allocated for phase 3 of the project is R800 000. The amount spent is R357 441.

Table 1: Financial summary phases 1, 2 and 3 of Resource Directed Measures, and Phase 1 of the capacity building and awareness creation project.

   

Budget 97/98

Spent 97/98

Budget 98/99

Spent 98/99

Budget 99/2000

Spent 99/2000

Budget 99/2000

Phase 1 (Jul 97 - Mar 98

200,000

206,383

         
Phase 1 (Apr 98 - Jul 98)    

300,000

304,654

     
Phase 2 (Aug 98 - Mar 99)    

660,000

649,510

     
Phase 3 (Apr 99 – Mar 2000)        

800 000

Extension (650 000)

357 441

 
Phase 1 (Apr 99 – Mar 2000)            

800 000

Totals

 

200,000

206,383

960,000

954,164

800 000

Extension of budget awaited

357 441

Approval awaited

A submission for the extension of the budget for phase 2 and 3 (R650 000) was submitted to MANCO for approval. Approval is urgently awaited to ensure the continuation of all the subtasks. The work will need to be terminated by the end of August 1999, if the approval for the extension of budget is not received by the beginning of August.

A submission for Phase 1 of a capacity building and awareness creation project was submitted to MANCO. The estimated budget for the proposed three year project is R2 million, with R800 000 allocated for the first financial year. Approval for this project is urgently awaited.

2.2 Steering Committee

A steering committee meeting has been scheduled for 18 June 1999, and will be held on 16 July 1999 in head office, DWAF. The following new members will join the steering committee:

Mr Geoff Cowan, representing the Department of Environmental Affairs and Tourism

Mr G McConkey representing the regional offices of DWAF.

2.4 Project office

Due to the scope and complexity of the RDM project, which is a multi-institutional, inter-disciplinary effort, a formal project office was established at the beginning of Phase 3 in April 1999. Dana Grobler of IWQS will be responsible for project administration and buffer management; Heather MacKay will continue with the overall technical and management responsibility for the project; Carol Nkwentsha (wlsec@dwaf.gov.za) replaces Luccrecia Mkondo, taking over liaison and co-ordination.

2.5 Departmental implementation workshop

Mr Grobler presented a talk at the workshop, and the following issues were raised at the workshop:

Director-Generals and Deputy-Director Generals (Manco) should be targeted to communicate time frames and terminology and the implementation of the reserve determinations.

A document was prepared and distributed by H MacKay to standardise the terminology:

3. progress on individual sub-projects AND ACTIVITIES

3.1 PIENAARS RIVER PILOT STUDY

The Pienaars river pilot study will be undertaken from 02 – 06 August 1999. The main purpose of the pilot study is to:

The following members from DWAF line functions were invited to attend and participate in the activities during the pilot study:

Ms Manda Hinsch (WQM)

Mr J Mare (Gauteng region)

Mr J Van Rooyen (Gauteng region)

Mr B Havenga (Planning and Mr P Van Rooyen – Consultant for Planning)

3.2 IMPLEMENTATION STRATEGY

The development of an implementation strategy for RDM was initiated during May 1999. As the date for full implementation of the Water Act draws near, there is a need to consider the implementation of what is, for the Department, a very new set of policy and regulatory tools, requiring new expertise and a different management approach from the past. At the request of the Chief Director: Scientific Services, a new sub-project has been established in the RDM team to take on the development of an implementation strategy for RDM and to guide the implementation initially until it can be handed over to an appropriately staffed and resourced line function

The objectives of the RDM Implementation (RDMI) team are:

Some initial work has been done to begin prioritising expected RDM implementation requirements, and this will be continued and extended over the next few months under the leadership of Dr H MacKay and Mr JN Rossouw.

The implementation team will be working with representatives of all the regional offices and relevant line functions in order to identify in some detail:

In order to generate this information, assistance from the regional offices and line functions will be necessary, and the relevant directors have been requested to nominate suitable members of their staff to participate in a series of workshops to be held later in the year.

The expected programme of activities required in order to identify and schedule RDM implementation priorities is outlined in Table 2 below.

Table 2: Proposed programme of activities for 1999

June 1999 Inform regional office and line functions, identify and nominate people to participate in prioritisation workshops, set dates for the workshops HM & JNR
August 1999 Prepare detailed briefing documentation explaining content and format of information required from the regional offices and line functions HM & JNR
Mid-September 1999 Distribute briefing documentation to the nominated participants HM & JNR
September - October 1999 Detailed templates and procedures for prioritisation to be used at the workshops will be developed by the RDM implementation team HM & JNR, RDM implementation team
September - October 1999 Participants collate the required information for the water management areas in their regions or according to their responsibilities. Nominated participants
25 October to 12 November 1999

Exact workshop dates to be set.

Prioritisation workshops to be held in Pretoria. A one-day workshop for each region, split into sessions on water quantity RDM requirements and water quality RDM requirements HM & JNR, RDM implementation team, nominated participants
mid-November 1999 Optimisation of master schedule using information from all the regional offices and line functions. Matching to present and future available capacity. RDM implementation team
December 1999 Visits to each regional office and line function to discuss the draft optimised RDM schedule and modify where necessary or develop short term contingency plans with the region. HM & JNR

As part of the development of the implementation strategy, the Western Cape regional office was visited during June 1999 to determine their requirements for incorporation in the generic strategy. H MacKay, D Grobler, T Duma and T Belcher from the IWQS, with N Rossouw (water quality and implementation subtasks) and S Fowkes (capacity building subtask) attended the meeting.

 

3.3 CLASSIFICATION

The ecosystem component of the resource classification system has been developed in considerable detail during the RDM project. The basic human needs and water users’ components are based on the existing Department documents "Domestic Water Quality Assessment Guide" and "SA Water Quality Guidelines".

The conceptual framework for the full resource classification system is based on a three-class system, which incorporates ecosystem protection, basic human needs protection and water users protection as follows:

 

3.4 RIVERS

3.4.1 Water quality

Further refinements of the methods based on experienced gained in the application of the methodology to the Olifants River study were conducted by the water quality task team, two modifications were made:

Work will now focus on converting the documentation into the format required for integration into the final technical documents.

3.4.2 Pienaars pilot study

The work of the rivers team focussed on the planning and preparation for the Pienaars River pilot study.

An integrated list of actions attached to each of the Reserve steps were provided and adjusted. The objective of the pilot study is to end with a ‘real’, i.e. workable intermediate determination (old PERM) for quantity, quality and groundwater.

It was also decided that an important focus during the pilot study is to develop the yield and operating procedures. A meeting between the IWQS, the rivers task team and Mr J van Rooyen was held to discuss the matter and to request that they task somebody to be involved in the process. During the discussion it became apparent that a model for the system exists and will require some updating. Pieter van Rooyen (a consultant) will be appointed by Mr Havenga to update the model and to participate during the relevant sessions in the pilot study. The model will be run at the workshop. The procedures will therefore be developed through the real application on the Pienaars River.

The pilot study has been initiated and the following (quantity) tasks have been undertaken:

The PERM sites have been identified.

The locality and an initial map have been distributed.

A cross-sectional survey has been undertaken and hydraulic data been collected.

A stream classification (Roy Wadeson) has been undertaken and has been distributed.

A draft programme for the pilot study has been designed and distributed for comment.

3.4.3 Desktop estimate (previously called planning estimate)

A meeting was held during which the method developed by D Hughes and the Tennant/Sellick approach was discussed.

The Hughes approach has more significance in the South African context as it is based on more rivers than Tennant, the rivers are South African and are varied in size and hydrological characteristics. However, a lack of data exists for seasonal and perennial rivers, and it was felt that the ‘curves’, are not conservative enough. To adjust the curves, a link between ecological habitat and the hydrology must be investigated. Water Resources Management is now funding a study whereby 4 rivers selected by Neels, Jay and Denis will be used to establish the shape of the curves at the drier end. The rivers all have a required hydrological index and are the Matlabas (index of 27), Shingwedzi (index of 20), Bushmens (index of 54) and Gonube (index of 16). Hydraulics will be available for the 4 rivers and a ‘mini’ IFR will be undertaken for each to come up with total volumes for additional points on the curves. A discussion session on how to adjust the curves based on this information will also be undertaken. Even though this will not provide high confidence estimates, it will provide some data where at present there is nothing.

3.4.4 Ecoregional mapping

A one-day workshop was held in June to develop terms of reference for the project to map level II ecoregions for South Africa. Additional funding was requested to carry out this work in the 1999/2000 financial year: once confirmation is received regarding the amount of funding which is actually available, the terms of reference can be submitted to the Control Committee and the project initiated. If the work is to be funded from the present RDM budget, then the scope of work for 1999/2000 will have to be scaled down considerably.

3.5 GROUNDWATER

A two day workshop was attended by Dr H MacKay and Mr Parsons to plan the activities of the WRC project on the comprehensive determination methodologies currently under development.

Mainactivities of Mr Parsons during May

- worked on groundwater document and case studies

- development work on reference conditions and current status

- collected data for Pienaars River pilot test

- presentation to GWD (Cape Town, Pretoria)

- discussions - Dr Tredoux (CT)

- discussions - Mr Conrad (CT)

- discussion - Mr Woodford (CT)

Main activities of Mr Parsons during June

- collected data for Pienaars River pilot test

- field visit to Pienaars River area

- discussions - Mr Orpen (Dwaf - Pretoria)

- discussions - Mr Xu (DWAF - Pretoria)

- discussions - Mr Pietersen (WRC - Pretoria)

- discussion - Mr Hobbs (VSA - Pretoria)

 

3.6 ESTUARIES

3.6.1 Estuarine freshwater requirement document

There have been a number of studies on the freshwater requirements of estuaries (e.g. Palmiet, Mhlathuze, Nhlabane, Tugela, Olifants, Mkomazi). The approach used in these studies has been documented. Comments from the estuarine reserve group were included in the final document.

3.6.2 Desktop estimate (Planning estimate)

A desktop estimate was determined for Eastern Cape Rivers on a quaternary basis. This study ignored the freshwater requirements of estuaries and this was thought to be a serious omission as for certain types of estuaries the freshwater requirements may be higher that the instream flow requirements. For this reason the Eastern Pondoland Coastal Basin Study (EPCBS, Transkei) undertook to determine a planning reserve estimate for sixteen estuaries in this area. A two day workshop was held. On day 2 a desktop estimate method for estuaries was refined. This method has been written up and will now be sent out to the estuarine reserve group for input.

Project planning funded a study on the planning estimate for 16 Pondoland (Northern Transkei) estuaries. Dr Janine Adams reported that the Desktop Estimate for 16 estuaries had been completed. A report was compiled, sent out for comment and will be finalised.

3.6.3. Intermediate determination (old preliminary method)

Work during 1999 will focus on developing a intermediate determination (preliminary method). Due to budget constraints the pilot study will only take place next year. A possible site for this study is the Mtata estuary. The Mtata River basin This study has been given the go-ahead by project planning.

3.6.4 Other

B Weston and A Whitfield attended a workshop held by Marine and Coastal Management. The implications of the Marine Living Resources Act were discussed. Ms Barbara Weston presented the New Water Act at the workshop. Other coastal legislation was discussed as well as the linkages between the different Acts.

A pilot study will take place in 2000 - a possible site being the Mtata Estuary. This pilot study must incorporate river, wetland and groundwater components and should be discussed by this integration team.

3.7 WETLANDS

The 7th Conference of Parties to the Ramsar Convention on Wetlands was held in Costa Rica in May 1999. Dr H MacKay participated as a member of the South African delegation to the meeting, along with Geoff Cowan, Dr Rod Randall and John Dini of DEAT, and Fadl Nacerodien of Foreign Affairs.

One of the major themes of the meeting was "Ramsar and Water". It has been recognised by the Convention that in order to ensure the protection of wetlands, including Ramsar-listed sites and others, wetland ecosystems require protection under water policy and law as well as under environmental and biodiversity legislation. Countries which have signed the Ramsar convention are being encouraged by the Convention to undertake reform of national water policy in order to promote more effective protection and sustainable use of wetlands. South Africa’s water policy and law was recognised as being "state of the art" in this respect, and generated a considerable amount of interest.

During the reporting period a draft discussion document was prepared drawing together the outcome of the January workshop and limited literature review to outline a conceptual approach to determining the Reserve for wetlands. The draft was circulated and useful comment was received which will be incorporated in the further development of the methodology. The document precipitated new contacts with researchers and sources of information related to wetland work underway in South Africa. The results of a thorough search on the WaterLit database are being processed at the moment. Mary Jean Gabriel has made several contacts in the USA.

The approach proposed in the discussion document will form the basis of the joint pilot study with the Rivers and Groundwater RDM groups on the Pienaars River at the beginning of August. A classic floodplain type wetland about 20 km long is located on the Pienaars River and will provide a good opportunity to test some of the concepts and further develop the methodology in a workshop environment. Fieldwork and data gathering for the pilot study are underway at present. The survey of the cross sections for the Wetlands Reserve pilot study was conducted during June 1999, assistance form Geomatics is greatly appreciated. Ms Gabriel and one more technician from IWQS attended the field work.

A link between the wetland task team has been made through the Rennies Wetland Awareness Campaign, with the Forestry industry initiative to develop tools for wetland delineation.

3.8 CAPACITY BUILDING

A capacity building and awareness creation strategy document was finalised.

The capacity building team have established formal links with the WRC for capacity building.

Ms Fowkes (team leader for capacity building) had a successful meeting with Ms Barbara Schreiner and Mr Marion Sekati regarding DWAF’s capacity building initiatives.

The first two-day introductory course on RDM determination was held on 30 and 31 March 1999 in Pretoria. It was attended by 34 Department officials. All the regions (water resources, water quality and geohydrology) and several head office directorates were represented. The feedback was very positive. Comments received on the course content and structure have been incorporated into the design of the next course.

The dates for the next training courses are:

3.9 COMMUNICATION

The first copy of the Water Act News was prepared and 6000 copies printed. Copies were distributed to about 25 categories of stakeholders. These included district councils, all DWAF offices (forestry and water), all provincial government departments, all libraries, mining, industry, international companies, every Working for Water office in the country and Metropolitan Councils.

Several comment sheets were received. Comments included the following requests:

An additional 1000 copies were printed during June 1999.

A factsheet which focussed on the use and protection of resources as well as an explanation of the Reserve, had been compiled and will be distributed in 4 languages. Target audiences for the factsheet would include companies that are seeking ISO 14000 status, paper industries, Working for Water project offices, amongst others.

The following tasks were performed during the reporting period:

Finalised stakeholder database

Distribution of 6 000 newsletters to whole RDM database

Receiving comment sheets and captured on database for evaluation report

Compiled first draft of evaluation report.

Various requests for extra copies of newsletter received:

Magda Ligthelm, DWAF, Mpumalanga - 500

Department of Agriculture, Pretoria, - 100

Project leaders within MGM took to various meetings to distribute

Bongi from DWAF, Pretoria, - 1500 to go out with Borehole Association

various incidental requests

Distributed media release with newsletter (250 papers and journals)

Finalised Communication plan and distributed to key members of Integration Team

First draft of fact sheet for previously disadvantaged readers of low education sent to Dr Van Vliet and Dr MacKay for comment

RDM overheads were prepared and distributed to Integration Team members via e-mail for their use

 

  1. CROCODILE RIVER 2000

A full scale demonstration project for resource protection policy will be established in the Crocodile River catchment, Mpumalanga, from January 2000. Dirk Roux will be the study manager. The initial partners in this project are DWAF and the CSIR. A proposal has also been submitted to WWF International for funding under their Living Waters Campaign.

APPENDIX A: DRAFT RDM MASTER SCHEDULE OF DELIVERABLES

    Desktop (Planning level) RDM Intermediate (Preliminary level) RDM Final (Comprehensive level) RDM
    Classification Reserve RQO Classification Reserve RQO Classification Reserve RQO
River ecosystems                    
  Apr 99 b b X a a a      
Delana Louw Oct 99 Final Final X b b b F F F
  Jan 01 - - X Final Final Final b b b
  Jan 04 - - X - - - Final Final Final
Groundwater resources                    
  Apr 99 b b X a a a      
Roger Oct 99 Final Final X b b b F F F
Parsons Jan 01 - - X Final Final Final b b b
  Jan 04 - - X - - - Final Final Final
Estuaries ecosystems                    
  Apr 99       F F F      
Janine Adams Pilot 99       a a a      
& Barbara Oct 99 Final Final X b b b F F F
Weston Jan 01 - - X Final Final Final b b b
  Jan 04 - - X - - - Final Final Final
Wetlands ecosystems                    
  Apr 99       F F F      
Andrew Aug 99       a a a      
Duthie Oct 99 Final Final X b b b F F F
  Jan 01 - - X Final Final Final b b b
  Jan 04 - - X - - - Final Final Final
Basic human needs RDM                    
  Oct 99 Final Final X b b X b b X
Adhishri Jan 01 - - X - - X Final Final X
Singh ? Jan 04 - - X - - X - - X
Water users RDM                    
  Oct 99 Final X X b X X a X X
Toni Jan 01 - X X - X X Final X X
Belcher Jan 04 - X X - X X - X X

 

Legend and abbreviations:

RDM Resource directed measures Includes classification system, procedures for selecting future management class, procedures for setting reserve, procedures for setting resource quality objectives
RQO Resource quality objectives Habitat and biotic objectives, mainly descriptive
WMI Water management institution Includes DWAF regions, or catchment management agencies, or licensing agencies
WRM Water resource management Includes allocation planning, catchment management, licence evaluation, monitoring & review
NWRS National Water Resource Strategy  
X Not applicable  
- No additional development scheduled  
F -version "Zero"-version procedures Outline of approach only, agreed by specialist team, detail of each step must still be developed
a -version "alpha"-version procedures Working prototypes, agreed by specialist team, ready for pilot testing by team and limited testing in selected real applications
b -version "beta"-version procedures Developed and tested procedures, to be refined after real applications around SA by a wider group
Final version Final version of procedures Fully developed and tested procedures, ready for publication in the Gazette

 

Appendix B: Layout of the suite of RDM documents

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Example layout for rivers technical procedure document

 

WATER RESOURCE PROTECTION AND ASSESSMENT POLICY IMPLEMENTATION PROCESS

RESOURCE DIRECTED MEASURES FOR PROTECTION OF WATER RESOURCES:

RIVER ECOSYSTEMS COMPONENT

Report number:

Team Leader(s):

Senior Author(s):

Editor:

PROPOSED TABLE OF CONTENTS

Section A: RDM Integrated Document (repeat) (HM)

 

Section B: RDM for River Ecosystems

Overview of all levels

Non specialist

For study managers and technical integrators

Rules for selection of levels (more detail than in Integrated document)

Section C: Procedure for desktop determination of RDM

Outline of steps, refer to appendices for each step

Section D: Procedure for rapid determination of RDM

Section E: Procedure for intermediate determination of RDM

Outline of steps,refer to appendices for detail. The old Part 4 text from the integrated report represents the appropriate level of detail for this section

Section F: Procedure for comprehensive determination of RDM

 

SPECIALIST APPENDICES

R1: Importance and sensitivity rating (CJK)

R2: Social importance rating (JO/RT)

R3: Economic values of ecosystem services (MM)

R4: Ecoregional typing to level II (CJK/LH/CT)

R5: Stream classification to level IV (RW/KR)

R6: Site selection (DL)

R7: Hydraulic calibration and modelling (AB)

R8: Determination of reference conditions (Resource quality = flow, quality, habitat, biota) (?/DL/JNR/CJK)

R9: Rapid present ecological status assessment (CJK/RT)

R10: Intermediate habitat integrity assessment (NK)

R11: Comprehensive habitat integrity assessment (NK)

R12: Ecological classification for river ecosystems (HM/?)

R13: Rapid/Desktop quantification of flow component using Hughes method (DH)

R14: Intermediate quantification of flow component using PERM(QN) method (DL)

R15: Comprehensive quantification of flow component (DL/HM)

R16: Determination of Resource Quality Objectives (LH)

R17: Extrapolation Guide (DH)

R18: Past IFR results (DH/VK/DL)

R19: Rapid quantificaition of water quality component (JNR)

R20: Intermediate quantification of water quality component (JNR)

R21: Comprehe