Pretty Pretty

Department of Water and Sanitation AND FORESTRY

CHIEF DIRECTORATE: SCIENTIFIC SERVICES

 

INCEPTION REPORT

MONITORING AND ASSESSMENT INFORMATION SYSTEMS

MAIS Phase 3

 

 

 

Draft for discussion and comment

March 2001

Table of Contents

1 Introduction *

1.1 Purpose of this Document *

1.2 MAIS Goal *

1.3 Critical Success Factors *

1.4 Background to MAIS Development *

1.5 MAIS Strategy *

1.5.1 Model for DWAF’s Water Monitoring and Assessment Information System *

1.5.2 Benefits of the MAIS Model *

1.5.3 Corporate Governance of MAIS *

1.6 Participation with Corporate Information Technology Management *

1.7 Collaboration with Water Resources Restructuring Initiative *

2 MAIS 3 Project Scope *

2.1 Project Deliverables *

2.2 Complex Knowledge Products *

2.3 Capacity Building in MAIS *

2.4 Corporate Infrastructure for MAIS *

2.5 Funding *

3 Project Plan *

3.1 Inception Module *

3.2 Initial Investigation Module *

3.3 Business Process Analysis Module *

3.4 Selected Integrated monitoring programmes Design Module *

3.5 Development of Generic Integrated Monitoring Programme Design Guides *

3.6 Development of an Implementation Plan *

4 Communication and Capacity Building *

4.1 MAIS 3 Task Team *

4.2 Stakeholders *

4.3 Human Resource Capacity Building *

5 MAIS 3 Project Management Structure *



List of Tables

Table 1 Phases in MAIS strategy development and implementation *

Table 2 Identification, roles and responsibilities of stakeholders in MAIS 3 *



List of Figures

Figure1 Necessary conditions for the proposed Monitoring and Assessment Information System (MAIS) and two prerequisites that are dealt with outside this strategy 3

Figure 2 Functional model of MAIS, showing the three key functional components shared by the portfolio of integrated monitoring programmes that comprise MAIS 3

Figure 3 Provisional infrastructure for MAIS 5

Figure 4 Examples of complex knowledge products derived from MAIS information products 9

Figure 5 MAIS 3 project structure 17

Monitoring and Assessment Information Systems

Analysis, Design, Implementation Plans and Capacity Building

MAIS 3

  1. 1. Introduction

    1.1. Purpose of this Document

    The history, scope, the proposed process to achieve the project objectives, and the project schedule for Phase 3 (MAIS 3) of an effort to co-ordinate water monitoring and assessment of the Department of Water and Sanitation (DWAF) are presented in this document.

    This inception report serves as a discussion document for role players who will participate in the project. Its intended audience has four components; (1) DWAF management who provide approval and the mandate, (2) project members who will be directly involved in activities, (3) DWAF staff who are monitoring and information stakeholders, and (4) key external stakeholders.

    The proposed process to achieve the project objectives has been described in this document. There are likely to be changes to the details of the process as greater understanding develops during the course of the project. Stakeholders are requested to comment on the approach and suggest solutions to perceived weaknesses so the approach can be refined or modified.

    1.2. MAIS Goal

    The overall goal of this multi-phase initiative is to construct a Monitoring and Assessment Information System (MAIS) that delivers water-related information that is effectively used for decision-making in institutions involved in water management. The date by which all the significant milestones should have been accomplished is April 2004.

    The results of this phase will strengthen the link between information use and available data by providing a structured process to design integrated monitoring programmes based on specific information requirements. A MAIS master system plan (MSP) for the information system will be developed as part of the project and subsequent applications will conform to the MSP and/or add functionality as needed. The MAIS MSP will be integrated into the overall DWAF MSP. Additional project components will address procedures to ensure adequate skilled capacity can be developed and to identify issues of corporate governance of the MAIS.

    Application of the integrated monitoring programme design process to areas not covered in this project’s pilot study will be planned in the final stages of this project and executed under subsequent phases or other projects.

    1.3. Critical Success Factors

    The success of this effort depends on the presence of:

    1.4. Background to MAIS Development

    An analysis of DWAF’s monitoring and assessment capability was initiated in response to mandates created by new water-related legislation and changing requirements from information users. Table 1 describes the activities conducted in earlier phases of MAIS and the output from each phase.

    Table 1: Phases in MAIS strategy development and implementation

    MAIS Phase

    Activities

    Output – Recommendations

    1

    Conducted in late 1999 – described stakeholder concerns related to DWAF’s efforts to create and manage water information

    A strategy should be developed to address the identified concerns.

    2

    Conducted in early 2000 – Clarify the concerns and develop the strategy (described in Section 1.5 below)

    Strategy accepted by DWAF Water Resources Management Committee and approved for implementation by DWAF Management Committee

    3

    This project – Initial investigations to determine general data requirements, conduct detailed analysis of selected requirements, develop generic integrated monitoring programme design guides, and integrated implementation plans to apply the design guides, build capacity, and establish requirements for MAIS corporate governance.

    1.5. MAIS Strategy

    A clear consensus emerged from stakeholder concerns that more integration is needed with respect to providing relevant, consolidated information for different hydrological components (for example, surface and ground water) with excellent, stable, and consistent information technology (IT) platforms. The MAIS strategy, therefore, focused on the need to provide a more co-ordinated effort to identify, produce and use relevant, water-related information.

    Four conditions, as shown in Figure 1, were identified during Phase 2 that are together necessary and sufficient for the establishment of an integrated MAIS. Two prerequisites were also identified that are not directly part of MAIS, but must be completed by others in collaboration with MAIS, in order to successfully accomplish the objective. The prerequisites are (1) corporate governance of IT in DWAF is effective in establishing consistent data management, access, and storage and (2) the organisational structure and business processes of the Department accurately reflect its mandate and core functions.

    1.5.1. Model for DWAF’s Water Monitoring and Assessment Information System

    A functional model, developed in Phase 2, for DWAF’s Monitoring and Assessment Information System underpins the strategy. The model is shown in Figure 2. Its main features are a number of monitoring and assessment programmes (hereafter referred to as integrated monitoring programmes) that all have the same functional components, namely:

    3. Project Plan

    Implementation of the MAIS strategy is planned for execution in six modules that are described in the following sections.

    3.1. Inception Module

    This inception module is a detailed planning exercise to construct plans for the project at sufficient detail for execution of the initial activities, with more general plans for later modules.

    The output from the module will be

    3.2. Initial Investigation Module

    The initial investigation module is the initiation of the plans developed during the inception phase. Assembly and analysis of background information to create an operational definition of complex knowledge products will comprise the first major set of activities. Stakeholders involved in the production of the complex knowledge products that serve the main water management functions of the Department will be identified and interviews conducted with them to develop a description of their information needs. Results will be used to describe a consolidated set of the information required as input to the combined set of complex knowledge products. Results of the interview analysis will also include:

    A description of existing monitoring activities – data acquisition, data storage and management, and information generation and dissemination – will be compiled as a parallel activity. The description will include the present delineation of monitoring programmes and the rationale for the delineation. General descriptions of human resource skills applied to design and operations will also be included.

    Communication with stakeholders will begin with this module, including constitution of a Task Team to facilitate project co-ordination and communication, presentations to a wide range of stakeholders who will be affected by project activities, and orientation sessions with those identified as critical to the production of complex knowledge products.

    A capacity building plan that describes in general the approach to develop sufficient expertise to operate and maintain MAIS during and after Phase 3 will be developed. Concurrent project capacity building activities will be initiated, primarily the identification and secondment of selected DWAF staff who will participate in the interviews and subsequent analyses.

    Preliminary investigations to identify potential sources of funding will also form a component of this module.

    The final component of this module will be the construction of detailed plans for the analysis and design module that follows.

    Business Process Analysis Module

    This module will increase the detail of the analysis begun in the previous module. The business processes required to produce the groupings of information requirements identified in the Initial Investigation will be agreed.

    The analysis will identify inputs, governing controls, outputs and mechanisms required to produce the information. Inputs will be broken down to the point where data requirements can be identified. Mechanisms required for relevant activities will be described in terms of information system requirements, including items such as statistical analysis, human resource skills, and technical infrastructure. Controls that govern the activities will be described in terms of policies and procedures required, guidelines, and other related items. Those requirements that are similar in several related activities will indicate the need for co-ordination in MAIS governance. Specialists in business process analysis, information provision, and integrated monitoring programme design will comprise the teams conducting the information gathering and analysis.

    The results of the analysis will be documented in a report that consolidates all the data requirements identified as essential to the inputs and the analyses required to produce specific information during generation of information products. Feasible integrated monitoring programmes will be identified that combine related data acquistion and analysis requirements and create optimum synergy by their combination. More specific criteria for inclusion in a integrated monitoring programme will be developed during the analysis.

    Detailed plans for the subsequent design module will be developed following this analysis.

  2. 3.4. Selected Integrated Monitoring Programmes Design Module

    The integrated monitoring programmes identified in the previous module will be designed by specification of criteria for:

    The design process will include participation by both information users and information providers to ensure an opportunity for negotiation of a feasible design that meets the information needs to the maximum extent possible within practical limits. The intention is to design a integrated monitoring programme that will provide the information required to produce the complex knowledge product. This is likely to include acquisition of data collected from other agencies. Liaison mechanisms will be required and will be addressed as part of the design process.

    Capacity building and extension of project resources is addressed in this module though the use of DWAF staff assigned to the project to assist in the design activities.

    3.5 Development of Generic Integrated Monitoring Programme Design Guides

    The design process followed in the previous module will be documented as a generic process for application to other information products. The Guides are intended to serve as reference documents for continued MAIS implementation and will contain relevant design criteria and standards.

    3.6 Development of an Implementation Plan

    The implementation plan will be based on knowledge gained during the execution of the project activities. Implementation priority selection will be informed by the results of the initial investigation and the scope of the integrated monitoring programmes designed. Results of the investigation of funding sources will also influence implementation priorities.

    Experts in application of information technology to business processes will refine and add detail to the MAIS master system plan for the information system, under supervision of the DWAF IT Integrator. The proposed framework for MAIS corporate governance will be refined with additional detail during the analysis and documented in a report to management.

    4. Communication and Capacity Building

    4.1 MAIS 3 Task Team

    On-going communication will be effected through the establishment of an inter-directorate Task Team on monitoring information. The Task Team should comprise stakeholders who are information providers, information users, and information technology specialists.

    The role of the proposed Task Team would be to provide input to the MAIS project team, review progress, provide liaison within DWAF Directorates, and review interim deliverables. This mechanism would play a major role in securing broader DWAF input into the design process and dissemination of project learning. The Task Team will have meetings and workshops outside their normal operations, therefore, there must be formal agreements with their supervisors and understandings with their colleagues. Each member will act as a communication representative who will facilitate the flow of information between stakeholders and the project team.

    The overall purpose of the Task Team will be to address;

    4.2. Stakeholders

    Stakeholders are persons, groups or institutions who will be affected by the changes to the status quo, or those who have vested interests in these changes. MAIS, by its integrated nature attracts a variety of stakeholders. The challenge is how to involve all the stakeholders to gain maximum mutual benefit from their participation. A coordination process must ensure stakeholder efforts complement and reinforce each other, leveraging resources while avoiding duplication and irrelevance.

    Effective stakeholder involvement will be a critical component of MAIS. A stakeholder communication strategy for MAIS will be developed as part of the Initial Investigation. A major objective of the communication strategy is to achieve a wide understanding of and support for MAIS as a corporate water information system. There must be broad stakeholder participation to enhance ownership of, and accountability for, project outcomes. The successful implementation of the communication strategy requires a communication network, adequate funding, and adequate specialist skills. The main stakeholders identified in the strategy and their roles and responsibilities are outlined in Table 2. Information exchange will be continuous throughout the project to obtain stakeholder input and to provide technical information that would help stakeholders embrace the new technology, its management, and the resultant change. Information provision will address the availability and distribution of timely and relevant project information, appropriate notification and proper stakeholder access to it. Communication mechanisms with stakeholders will vary among the distinct groups identified. Presentations to describe plans, status, and obtain feedback and request approval to proceed will be the most common mechanisms for interactions with DWAF management.

    Human Resource Capacity Building

    Access to the required HR capacity is a key success factor to the development, implementation, maintenance and effective use of MAIS. A capacity building strategy will be developed as a component of MAIS 3 after a preliminary skills assessment during the initial investigation. The objective of the strategy is to establish institutional capacity within water management institutions to develop, maintain, and use MAIS. The required capacity consists of;

    A human resource development plan will be established during MAIS 3 and implemented as part of MAIS 4 or in other projects.

    It is envisioned that a significant amount of capacity building will take place during MAIS 3. For example, the enhancement of the capacity required for the MAIS core team could be achieved through the participation of Task Team members in the design and development of MAIS.

    Candidates from DWAF staff will be identified and requested to participate in various parts of the project from inception through to roll-out. It is envisaged that this group will be mainly from Directorates responsible for providing water-related information and will contribute to the initial investigation and subsequent design components.

    Table 2: Identification, roles and responsibilities of stakeholders in MAIS 3

    Stakeholder

    Composition/Description

    Mechanism for communication

    Role

    Water Resources Management Committee

    Deputy Director General: Water Resources, Chief Directors, and Directors

    Presentations and reports

    To provide strategic direction

    CD:Scientific Services

    Chief Director

    Presentations, reports, progress meetings

    Project Sponsor; review progress, approve interim deliverables and ensure alignment with DWAF strategic objectives

    D: IWQS

    Director, Project Manager, and various staff members

    Presentations, reports, meetings

    Project management; funding; project execution

    Information Providers

    Responsible for DWAF monitoring programme operations and delivery of information, represented in MAIS primarily by the Task Team

    Presentations, reports, working sessions, workshops

    Advise on and confirm data requirements and the design of MAIS; co-ordinate MAIS development process and ensure key stakeholders have been identified and consulted. Task Team will also facilitate collaboration between the project team and DWAF and relevant external information providers.

    Information providers external to DWAF

    Responsible for data production and delivery of water related information

    Presentations, reports, working sessions, workshops

    Advise on and confirm data requirements and the design of MAIS

    CKP owners (information users)

    Individuals or groups responsible for complex knowledge products that are used in DWAF water management

    Meetings, working sessions, interviews

    Provide input on information requirements and negotiate information product requirements

    Information users external to DWAF

    Individuals responsible for activities that require water related information

    Meetings, working sessions, interviews

    Provide input on information requirements and negotiate information product requirements

    Specialist Teams, including consultants

    Senior members of DWAF’s water resources directorates and external specialists who have a deep knowledge of DWAF's business or what the business should be

    Presentations, reports, working sessions,

    Confirm information requirements; participate in the initial investigation process and participate in the business process analysis.

    Restructuring team/s

    Consultants tasked with the restructuring of the Water Resources functions in DWAF

    Presentations, reports, working sessions, workshops

    Make input on recommendations for MAIS Corporate governance and infrastructure; update MAIS team on restructuring progress

    TINWA

    TINWA was established to monitor implementation of the NWA

    Submission of inception report, update project plan and progress

    Monitor key result areas of information management.

    Provide feedback to MAIS on achievement of plans.

    Integrator & CIO

    Supports DWAF’s information management processes

    Presentations, reports, working sessions, workshops

    Provide preliminary design for MAIS Master System Plan; Design and develop implementation plans for data storage and management infrastructure; Provide resources to lead business process analysis

    5. MAIS 3 Project Management Structure

    The integrative nature of MAIS will create an impact that will be felt in many of the water mangement functions of DWAF. The inclusive manner in which the project activities are planned will also require input from a number of distinct organisational units. A project reporting structure has been designed to address the need for co-ordination, communication, and defined approval routes. Because an integrated approach to information management is a mission critical requirement in DWAF, reporting to senior management is an essential component

    A strong interface with DWAF’s corporate IT is vital to the success of the planning and implementation aspects of the project. Figure 5 shows the schematic representation of the project reporting and collaboration structure.