			                The uMWP1 is a feasibility study for the transfer of water from the undeveloped 
                            uMkhomazi River to the existing Mgeni system to further augment water supply to 
                            the Durban and Pietermaritzburg areas. It is a multi-disciplinary project, 
                            undertaken conjunctively by the Department of Water and Sanitation (DWS) and Umgeni 
                            Water (UW).  
                                    Phase 1 of the uMkhomazi Water Project (uMWP1) comprises three modules: a raw 
                                    water module developing the resource and the transfer infrastructure (module 1), a treated 
                                    water module (module 3) and an environmental impact assessment module (module 
                                    2). 
                                    The modules have been and will be assigned to professional services providers to 
                                    address the following aspects related to a major water development: 
                                    
                                    Water resources: uMkhomazi, uMlaza and uMngeni River catchments;
  
                                    Water requirements: Water users in the uMkhomazi and uMngeni River catchments; 
  
                                    Engineering investigations: Proposed dams at Impendle (only for costing purposes) and Smithfield; the raw water conveyance infrastructure from Smithfield Dam via the proposed balancing dam at Baynesfield to the Water Treatment Plant; and potable water conveyance infrastructure to the Umlaas Road/Cato Ridge reservoir; 
  
                                    Environmental impact assessment: Smithfield Dam to Umlaas Road/Cato Ridge reservoir, including all conveyance infrastructure; and
  
                                    Socio-economic impact assessment: Regional, provincial (KwaZulu-Natal) and national.
  
                                     
                                    If the scheme is deemed feasible, in relation to other options, it may be 
                                        implemented by 2023.  
                            Once complete, the uMkhomazi water transfer scheme will be the largest water 
                                transfer scheme in South Africa, comparable to the Lesotho Highlands Water 
                                Project in terms of water volume and tunnel lengths and diameters.  
                              
                            
                            
                                 
                             
                                
                                    
                                        The Project Area
                        The project area focuses on the uMkhomazi River catchment. Some tasks within the 
                            overall project’s three modules will also include surrounding catchments (the 
                            uMngeni River and the uMlaza River catchments).  
                                         | 
                                     
                                         | 
                                    
                                     
                                         | 
                                 
                             
                          
                         
                             
                         |